TECHNICAL SELECTION NOTES · UPDATED 2026-10-01

Custom fiber assembly RFQ: drawings, BOM and acceptance

An effective RFQ includes the application, both interfaces, port map, fiber type, length definition, environment, mechanical envelope, performance targets, test method, quantity and sample plan.

DIRECT ANSWER / 01

Separate known requirements, targets and open items in a custom RFQ

A custom fibre assembly RFQ is a requirements package for joint review, not just a price request with length and quantity. Include application, mating parts, fibre and lane map, routing, environment, quantity and acceptance method; mark unknown fields as open.

Use this for OEM equipment, special harnesses, onboard routing and replacement assemblies. This workflow is procurement advice; the cited standards cover interfaces, measurement or inspection, not a mandatory RFQ format. Start with a discussion revision, then freeze the order through approved drawings and BOMs instead of defaulting to another supplier’s catalogue values.

SELECTION MATRIX / 02

Purchasing decision matrix

ItemIdentifyCorrect actionAvoid
InterfacesFull references and mating parts at both endsAttach drawings and define pins, key and end face separatelyProviding only a photograph
Optical pathFibre, positions, active lanes and branchesFreeze mapping with port IDs and viewing directionWriting only straight or crossed
MechanicsLength datum, envelope, bends and installationProvide a layout and critical tolerancesTreating a catalogue outline as a project drawing
PerformanceTarget limits and corresponding test conditionsObtain supplier feasibility and method confirmationRequesting a loss value without a method
Revision and quantitiesSamples, volume forecast, schedule target and document stateSeparate targets from approved requirementsTreating a target schedule as guaranteed lead time

RFQ INPUTS / 03

Minimum inputs a supplier can verify

CategoryRequired input or confirmation
Project briefApplication, equipment, known conditions, open items, sample count and volume forecast
Technical attachmentsEnd drawings, lane map, dimensions, BOM, revision and permitted substitutions
Acceptance packageInspection, mapping, optical tests, environmental validation scope, labels and reports

BUYER FAQ / 04

Purchasing FAQ

01

Can I inquire without a complete part number?

Yes. Provide equipment and interface photos, known dimensions and application; retain unknowns as review items.

02

Can a typical value be an acceptance limit?

Not automatically. Agree limits, methods and configuration and record them in approved documents.

03

Can the BOM change freely after sample approval?

Do not assume so. Agree change approval and revalidation scope and align sample and production revisions.

04

How should supplier quotations be compared?

Align interfaces, origin, construction, testing, labels and deliverables before comparing price; list all deviations.

05

What should be sent first?

Start with application, mating parts, route/length, quantity and target schedule; then add the lane map and acceptance requirements.

SOURCES / 05

Sources and applicability

Sources checked: 2026-10-01. This guide clarifies purchasing fields; it does not replace current equipment data sheets, full standards or the approved project drawing.

  1. US Conec — MTP brand MPO connectors
  2. IEC 61300-3-35:2022 — Connector end-face inspection
  3. IEC 61280-4-5:2020 — MPO-terminated cabling measurement

RFQ / ENGINEERING REVIEW

Send what you know. We will help define the rest.

Interfaces, fiber count, application, environment, quantity or a drawing are enough to start.

Open email to inquire

Send to: xsconcom@gmail.com · Your email app opens. Review the message and send it there.

Drawings, BOMs and existing samples are welcome
Talk to an engineer